Scripting efforts in performance testing
Source : SQA Forums : http://www.sqaforums.com/showflat.php?Number=583987
am looking at understanding what is effort in hours that goes in creating scripts.
I usually classify as simple medium and complex and allot around 6-8/10-14/18-24hrs of effort based on the application type/Protocol Used/Number of screens. ( this also depends on the scripter ).
Would like receive inputs on how experts do estimation for creating scripts/or experiences in effort required while creating performance testing scripts.
And I am not limiting myself to loadrunner, I am looking at most of the industry standard tools like SilkPerformer, Rational Performance Tester/WebLoad/JMeter/Grinder.
I usually classify as simple medium and complex and allot around 6-8/10-14/18-24hrs of effort based on the application type/Protocol Used/Number of screens. ( this also depends on the scripter ).
Would like receive inputs on how experts do estimation for creating scripts/or experiences in effort required while creating performance testing scripts.
And I am not limiting myself to loadrunner, I am looking at most of the industry standard tools like SilkPerformer, Rational Performance Tester/WebLoad/JMeter/Grinder.
==============================================================
(Number of Steps * Skew for Protocol * Skew for level of expertise for the scripter with protocol * skew for tool used * skew value for scripter expertise with tool) + (anticipated number of custom functions based upon examination of the app and business processes * 4 * Skew for level of expertise for the scripter) = estimated number of hours per business process scripted
So, if you have a new untrained scripter on a new protocol on a new tool with a couple of custom functions that need to be created and this protocol is winsock, then perhaps you wind up with a estimate range of
Assuming tool and protocol expertise
(8(steps) * [2.5 - 5.0] * 1 * 1 * 1) + (2 * 4 * 1) = Range of [28 to 48]
That gives you a generic formula. You will need to come up with your own values for protocol skew, tool skew, person expertise skew and the like.
So, if you have a new untrained scripter on a new protocol on a new tool with a couple of custom functions that need to be created and this protocol is winsock, then perhaps you wind up with a estimate range of
( 8(steps)
* [2.5 - 5.0](protocol Skew)
* [7 - 10](expertise skew-protocol)
* 1(tool skew)
* 2(Expertise with tool skew )
+ ( 2(custom functions)
* 4(hours)
* [7-10](expertise skew-protocol) )
Range of [336 to 880]
Assuming tool and protocol expertise
(8(steps) * [2.5 - 5.0] * 1 * 1 * 1) + (2 * 4 * 1) = Range of [28 to 48]
That gives you a generic formula. You will need to come up with your own values for protocol skew, tool skew, person expertise skew and the like.
For more information on this, click here